Implementing the project of technical design, procurement, processing, manufacturing, installation and trial operation of sour water pipes at Nghi Son Refinery and Petrochemical Plant

Implementing the project of technical design, procurement, processing, manufacturing, installation and commissioning of sour water pipes at Nghi Son Refinery and Petrochemical Plant

After 6 months from June 2021 to December 2021, PMS completed and handed over the project of technical design, procurement, processing, manufacturing, installation and test operation of sour water pipes at the Factory. Nghi Son petrochemical refinery

PETROLEUM MAINTENANCE SERVICES JOINT STOCK COMPANY (PMS)