Thousands of people bustling to work on the 5th BDTT construction site of Dung Quat Oil Refinery

THOUSANDS OF PEOPLE HURRY WORKING ON THE 5TH GREAT BDTT CONSTRUCTION SITE OF DUNG QUAT Refinery
(PetroTimes) - Entering the first week of the 5th general maintenance period of Dung Quat Oil Refinery, many important tasks are being raced against time by Binh Son Refining and Petrochemical Joint Stock Company (BSR) and contractors. towards the goals of safety, quality, schedule and cost optimization. Currently, the inspection, evaluation, repair... of equipment and machinery are being urgently carried out by experts, BSR and contractors to be ready to carry out major tasks in this maintenance period.
Hàng ngàn người hối hả làm việc trên đại công trường BDTT lần 5 NMLD Dung Quất
On the 5th BDTT construction site of Dung Quat Oil Refinery, more than 4,000 employees are rushing to carry out work items to ensure the set goals of safety, quality, progress and cost optimization.
Hàng ngàn người hối hả làm việc trên đại công trường BDTT lần 5 NMLD Dung Quất
BSR personnel and PMS contractor personnel are testing the MAB C-1501 air supply fan (also known as the compressor) designed to provide enough air for the complete combustion of coke in the equipment. regenerates and provides gas to maintain continuous catalytic circulation in the system.
Hàng ngàn người hối hả làm việc trên đại công trường BDTT lần 5 NMLD Dung Quất
At the CCR workshop, quality xThe catalyst inside will be temporarily stored in drums, brought to a safe location, the workshop will be cleaned, and maintenance will be performed.
Hàng ngàn người hối hả làm việc trên đại công trường BDTT lần 5 NMLD Dung Quất
At the CDU workshop, generator rotors are being inspected and taken for maintenance.
Hàng ngàn người hối hả làm việc trên đại công trường BDTT lần 5 NMLD Dung Quất
The catalytic cracking factory (RFCC), considered the "heart" of Dung Quat Refinery, is carrying out many major tasks in the 5th BDTT.
Hàng ngàn người hối hả làm việc trên đại công trường BDTT lần 5 NMLD Dung Quất
BSR personnel and PVMR contractor personnel are urgently implementing the work as planned.
Hàng ngàn người hối hả làm việc trên đại công trường BDTT lần 5 NMLD Dung Quất
The bustling working atmosphere at the project package No. 5 implemented by the PVMR - Toan Thang joint venture. This contract will maintain 1,280 valves at Dung Quat Oil Refinery.
Hàng ngàn người hối hả làm việc trên đại công trường BDTT lần 5 NMLD Dung Quất
Contractor personnel will check the valve condition, then make a repair and maintenance plan.
Hàng ngàn người hối hả làm việc trên đại công trường BDTT lần 5 NMLD Dung Quất
Heat exchangers are maintained using high pressure water jets.
Hàng ngàn người hối hả làm việc trên đại công trường BDTT lần 5 NMLD Dung Quất
High-altitude work with many participants requires precision and high concentration of maintenance personnel.
Hàng ngàn người hối hả làm việc trên đại công trường BDTT lần 5 NMLD Dung Quất
A contractor works in a cramped environment when entering a pipeline to clean catalyst residue.
Hàng ngàn người hối hả làm việc trên đại công trường BDTT lần 5 NMLD Dung Quất
Welding jobs that generate heat must be carried out in safe conditions, without fire.
Hàng ngàn người hối hả làm việc trên đại công trường BDTT lần 5 NMLD Dung Quất
Some positions working at height must always strictly comply with safety rules.

PETROLEUM MAINTENANCE SERVICES JOINT STOCK COMPANY (PMS)